Veliaj's next scam/ He said that the Babrroi bridge will be opened in June, the works are not finished

2024-07-03 17:56:00, Politikë CNA
Veliaj's next scam/ He said that the Babrroi bridge will be opened in June,
Photomontage - Babrroi Bridge and Erion Veliaj

"The Babrroi bridge that connects Tirana with Kamza will be opened for vehicles in the month of June."

This was the statement made by the mayor Erion Veliaj on May 23, while inspecting the works. At that time, he said that he felt happy that Kamza and Tirana had united in infrastructure.

"I can't wait to open it at the end of June, so that all those who will go between Kamza and Tirana, Babrru, Paskuqani during the summer, will feel a relief. I ask for the cooperation of the residents even when there are demolitions, especially for the demolition of constructions without permission, which, as seen now, have really become an obstacle. Long live us for having built the bridge, that when we are faced with illegal constructions on the other side, of course we will deal with them according to the rules of expropriation and reconstruction, but even they must accept that the city cannot be hindered", he declared. Veliaj.

CNA was this Wednesday (July 3) near the new Babrroi bridge to see more closely the progress of the works and if this work has really helped to ease the traffic of vehicles.

Veliaj's next scam/ He said that the Babrroi bridge will be opened in June,
Babrroi Bridge, source CNA

As can be seen from the images, not only have the works not been completed as promised by the mayor, but it still takes time for the bridge to be functional. Traffic continues on the old bridge, which does not allow two vehicles in different directions to pass at the same time, but they have to wait for traffic lights on both sides of the old bridge to move, thus bringing heavy traffic to area.

This is the next deception of the mayor of Tirana, who has often made hasty statements about the completion of works, many times to take credit and other times to show that he is working. Finally, his inspections in different places of Tirana have been part of the propaganda, to hide or fade the news about the thefts committed in the Municipality of Tirana, by the "5D" directors, who are behind bars.

Veliaj's next scam/ He said that the Babrroi bridge will be opened in June,
Babrroi Bridge, source CNA

Earlier, Veliaj gave incorrect dates for the start and end of works, for many road axes, for schools and nurseries, including the dates for the completion of works at the National Theatre. For the specific case, based on the footage on the ground, we ask the mayor a simple question: June has passed, when will the Babrroi bridge be finished?!/ CNA