Council of Ministers/ The construction of photovoltaic power plants in Povelça and Boçova, Fier, is approved

2025-06-04 15:57:00, Politikë CNA

Council of Ministers/ The construction of photovoltaic power plants in

At today's meeting of the Council of Ministers, the construction of two photovoltaic power plants in the villages of Povelçë and Boçovë, part of the Municipality of Fier, was approved.

It is learned that the power plants will have a capacity of 25 MW and 82 MW, respectively.

The time for construction, obtaining the construction permit and putting the photovoltaic plant into operation will be within 36 (thirty-six) months from the entry into force of this decision.

DECISION 

ABOUT

APPROVAL OF THE CONSTRUCTION OF A PHOTOVOLTAIC ELECTRICITY GENERATION PLANT AND AUXILIARY WORKS, WHICH IS NOT A CONCESSION OBJECT, IN CADASTRAL ZONE 3038, VILLAGE OF POVELÇË, ADMINISTRATIVE UNIT OF DËRMENAS, MUNICIPALITY OF FIER, DISTRICT OF FIER, BY THE COMPANY “POWER ENERGY”, LLC

In accordance with Article 100 of the Constitution and point 1, Article 49, of Law No. 43/2015, “On the Electricity Sector”, as amended, upon the proposal of the Deputy Prime Minister and Minister of Infrastructure and Energy, the Council of Ministers

DECIDED:

1. Approval of the construction of a photovoltaic power generation plant and ancillary works, which is not subject to concession and does not benefit from support measures, in cadastral zone 3038, Povelçë village, Dërmenas administrative unit, Fier Municipality, Fier District, by the company “POWER ENERGY”, sh.pk, with the elements as follows:

a) Name of the applicant: “POWER ENERGY” Company, sh.pk;

b) NIPT/NUIS: M32018028D;

c) Type of power plant: Photovoltaic;

ç) Installed capacity: 25 MW;

d) Expected deadline for commissioning and obtaining a construction permit: The time for construction, obtaining a construction permit and commissioning the photovoltaic plant will be within 36 (thirty-six) months from the entry into force of this decision;

dh) Location of the energy generating source: In cadastral zone 3038, Povelçë village, Dërmenas administrative unit, Fier Municipality, Fier District;

e) Operation period: 49 (forty-nine) years from the entry into force of this decision;

ë) Land coordinates and zoning plan according to Annex 1, attached to this decision;

f) The Ministry of Infrastructure and Energy and the National Agency of Natural Resources have the right to exercise general supervision with 3-month deadlines during the implementation, commissioning and operation, with the aim of verifying that the progress of the works, quality, conformity and operation are in accordance with the general implementation program and project documentation;

g) The company "POWER ENERGY", sh.pk, has the obligation to:

i. to periodically (every three months) submit to the Ministry of Infrastructure and Energy and the National Agency for Natural Resources, information on the progress of the construction of the photovoltaic power plant;

ii. to respect the conditions cited in the permits, licenses and prior environmental authorizations issued by the responsible national institutions;

iii. to submit the contract security, in the amount of not less than 5% of the investment value, before signing the contract between the company “POWER ENERGY”, sh.pk, and the ministry. This contract defines the rights and obligations of the parties for the implementation of this project, penalties, in case of non-implementation, as well as other issues related to its implementation;

iv. to provide free of charge, in the form of royalty, to the ministry responsible for energy the amount of electricity, at the rate of 2 (two) % of the annual amount of electricity production or its conversion into monetary value. In the case of conversion into monetary value, the amount must be paid entirely into the state budget;

v. to comply with the requirement, as applicable, that a portion of the production of the energy generating source be sold to the public supplier, in accordance with applicable legislation.

2. The Ministry of Infrastructure and Energy and the company "POWER ENERGY", sh.pk, are charged with the implementation of this decision.

This decision enters into force immediately and is published in the "Official Gazette".

***                  

DECISION

ABOUT

APPROVAL OF THE CONSTRUCTION OF A PHOTOVOLTAIC ELECTRICITY GENERATION PLANT AND AUXILIARY WORKS, WHICH IS NOT A CONCESSION OBJECT, IN CADASTRAL ZONE 2436, VILLAGE OF BOÇOV?, ADMINISTRATIVE UNIT OF LEVAN, MUNICIPALITY OF FIER, BY THE COMPANY “ALBANIA SOLAR POWER”, LLC

In accordance with Article 100 of the Constitution and point 1, Article 49, of Law No. 43/2015, “On the Electricity Sector”, as amended, upon the proposal of the Deputy Prime Minister and Minister of Infrastructure and Energy, the Council of Ministers

DECIDED:

1. Approval of the construction of a photovoltaic power generation plant and ancillary works, which is not subject to concession and does not benefit from support measures, in cadastral area 2436, Boçovë village, Levan administrative unit, Fier Municipality, by the company “ALBANIA SOLAR POWER”, sh.pk, with the elements as follows:

a) Name of the applicant: “ALBANIA SOLAR POWER” Company, sh.pk;

b) NIPT/NUIS: M41423083S;

c) Type of power plant: Photovoltaic;

ç) Installed capacity: 82 MW;

d) Expected deadline for commissioning and obtaining a construction permit: The time for construction, obtaining a construction permit and commissioning the photovoltaic plant will be within 36 (thirty-six) months from the entry into force of this decision;

dh) Location of the energy generating source: In cadastral area 2436, Boçovë village, Levan administrative unit, Fier Municipality;

e) Operation period: 49 (forty-nine) years from the entry into force of this decision;

ë) Land coordinates and layout plan according to Annex 1, attached to this decision;

f) The Ministry of Infrastructure and Energy and the National Agency of Natural Resources have the right to exercise general supervision with 3-month deadlines during the implementation, commissioning and operation, with the aim of verifying that the progress of the works, quality, conformity and operation are in accordance with the general implementation program and project documentation;

g) The company “ALBANIA SOLAR POWER”, sh.pk, has the obligation to:

i. to periodically (every three months) submit to the Ministry of Infrastructure and Energy and the National Agency for Natural Resources information on the progress of the construction of the photovoltaic power plant;

ii. to respect the conditions cited in the permits, licenses and prior environmental authorizations issued by the responsible national institutions;

iii. to submit the contract security, in the amount of not less than 5 (five) % of the investment value, before signing the contract between the company “ALBANIA SOLAR POWER”, sh.pk, and the ministry. This contract defines the rights and obligations of the parties for the implementation of this project, the penalties, in case of non-implementation, as well as other issues related to its implementation;

iv. to provide free of charge, in the form of royalty, to the ministry responsible for energy the amount of electricity, at the rate of 2 (two) % of the annual amount of electricity production or its conversion into monetary value. In the case of conversion into monetary value, the amount must be paid entirely into the state budget;

v. to comply with the requirement, as applicable, that a portion of the production of the energy generating source be sold to the public supplier, in accordance with applicable legislation.

2. The Ministry of Infrastructure and Energy and the company "ALBANIA SOLAR POWER", sh.pk, are charged with the implementation of this decision.

This decision enters into force immediately and is published in the "Official Gazette" ./CNA 

 

 

 

 