Camps for Italian immigrants/ "La Repubblica": The works in the first phase will be completed in November

2024-04-15 08:25:00, Aktualitet CNA
Camps for Italian immigrants/ "La Repubblica": The works in the first
The immigrant camp in Gjadër

The Italian media "La Repubblica" has made an article about the camp in Gjadër, where the immigrants coming from Italy will be accommodated.

"La Repubblica" writes that the work started on March 23 and will be delivered on November 10 of this year.

The article states that the works in the port of Shengjin and in the former military base of Gjadri are in the first steps and a number of difficulties are emerging from the inspections in the area.

The prime minister of Italy, Giorgia Meloni, aims for housing to start in May, but the Italian media points out that this is impossible.

Also, "La Repubblica" mentions the expenses that will be covered by Italy, which according to it are inflated and break the ceiling of 700 million.

Full article:

The start of work on March 23, delivery is expected after 233 days, that is, on November 10. This is what is written in the decision of the Ministry of Defense that entrusted military engineers with the construction of centers for immigrants in Albania. Which, however, according to the intentions of Prime Minister Giorgia Meloni and above all the tender for the management of the centers, should open their doors on May 20.

Construction sites just opened, it will take months

In the port of Shengjin and in the former military base of Gjadri, the works are in the first steps, inspections are being carried out which are highlighting a number of difficulties in the area. It is impossible that the centers will be ready by May, it will take months, the whole summer will pass. The first documents reveal the bluff, as the costs for the center in Albania continue to rise and risk reaching the figure of around one billion euros in five years. Because to the official figures, which amount to about 150 million euros per year multiplied by five years, the reimbursable costs at the bottom of the list, for transport and health care and, in terms of structures, subcontracts should be added.

Diverted extrabudgetary funds

Also, the costs of building two centers, that of the reception in the port of Shengjin and the camp in Gjadër, should be considered additional budget. The works entrusted to the engineers will cost around 65 million euros. Money which was partially taken from a draft law that deals with the use of Pnrr funds, as the opposition representatives underlined.

"Every day that passes the bluff of the Italy-Albania agreement becomes more and more clear, says Matteo Mauri. Costs increase every month. In a March decree, another 65 million euros were added, breaking the ceiling of 700 million. A disproportionate amount of money to do something completely useless."

The tender for the management of the centers has been awarded

In the following days, the Ministry of the Interior will announce the 36 million euro tender for the management of the centers. Under consideration are the offers of three companies selected from the thirty participants. Still to be announced is that for the supply of prefabricated modules to be placed in the areas when engineers and subcontractors have completed their excavation, reclamation, construction of sewers and systems, with no expense limit./ CNA